Please note: All dates and durations are approximate and subject to change.
The final cleanup and stabilization work has been completed on Calamo Street and repaving is currently underway. Repaving is expected to be completed around September 11th.
Once repaving is complete, Calamo Street will be reopened. At that time, a section of Spring Road will be closed for construction. This will be a continuous 24-hour closure lasting approximately 6 weeks.

After all work on Spring Road is completed, the section disturbed during construction will also be repaved.
Calamo Branch Stream Construction
Initial construction has begun along the Calamo Branch stream, located in the wooded area west of Ridgeway Drive. This construction is expected to continue through the end of 2026.
Other Upcoming Work in the Area
The following projects are not being performed by Weider Contracting, and we do not have schedule or timeline information for them:
- VDOT Culvert Replacement: Replacement of the existing stream culvert crossing from approximately 7203 Calamo Street to the intersection of Calamo Street and Spring Road.
- Gas Line Replacement: Gas line replacement work on Calamo Street following completion of our project.
We appreciate your continued patience and cooperation as we work to complete these important improvements. As dates and project information is finalized, additional information will be posted.