Project Work Update – August 7th

Please note: All dates and durations are approximate and subject to change.

Through End of August: Calamo Street Completion  

We are currently performing final cleanup and stabilization work on Calamo Street.

Daily flagging operations will continue in the intersection of Calamo Street and Spring Road for approximately the next 3 weeks while this work is completed.

Beginning Early September – Spring Road Construction Begins

Once work is complete on Calamo Street, it will be reopened.

At that time, a section of Spring Road will be closed for construction. This will be a continuous 24-hour closure lasting approximately 6 weeks.

We will provide additional notice as soon as the reopening date for Calamo Street and the closure date for Spring Road are confirmed.

Repaving

After all construction is complete, we will repave:

  • Calamo Street from Ridgeway Drive to Spring Road
  • The section of Spring Road disturbed by construction

We currently anticipate completing paving by end of October. Once paving dates have been finalized, we will provide additional information.

Calamo Branch Stream Construction

Beginning next week, initial construction activities will start along the Calamo Branch stream, located in the wooded area west of Ridgeway Drive. This construction is expected to continue through the end of 2026.

Other Upcoming Work in the Area

The following projects are not being performed by Weider Contracting, and we do not have schedule or timeline information for them:

  • VDOT Culvert Replacement: Replacement of the existing stream culvert crossing from approximately 7203 Calamo Street to the intersection of Calamo Street and Spring Road.
  • Gas Line Replacement: Gas line replacement work on Calamo Street following completion of our project.

We appreciate your continued patience and cooperation as we work to complete these important improvements. We will continue to provide updates as firm dates and additional project information become available.