Work Update for Week of March 17th

During the week of March 17th,  we will be performing construction operations on Calamo Street between Wren Drive and Spring Road. Any flagging or detour operations that occur will be during the allowable lane closure hours of approximately 9:00 AM to 3:30 PM.

Work to be performed this week:

  • Roadway saw cutting
  • Test pitting
  • Installation of temporary sewer bypass pipe. This work will require excavating trenches in front of driveways on the north side of Calamo Street. On site personnel will coordinate directly with affected homeowners.

This work is weather dependent and subject to change. Please visit the website at calamosewerproject.com for any additional updates and more information.