Work Update for Week of June 30th

During the week of June 30th, the continuous detour will remain the same. Until further notice, all access from Ridgeway Drive is closed and only residents will be allowed to use Spring Road to access Calamo Street. Please refer to the detour map below.  

We will not be operating on Friday, July 4th. However, the ongoing detour will remain in effect.

Our typical work hours will begin at 7:00 AM and continue to approximately 5:00 PM. As the construction progresses the detour may be modified, and we will communicate in advance of any changes.

We will continue to use steel plates to cover the excavation areas at the end of the day. Please always proceed through the work area with care and drive with caution at all times.  We strive to create an environment that is safe for you, your neighbors, and our employees.

This work is weather dependent and subject to change. Please visit the website at calamosewerproject.com for any additional updates and more information.