  • Work Update for Week of May 26th

    Next week there will not be any construction on Calamo Street on Monday in observance of Memorial Day but work will resume on Tuesday. The detours will remain the same next week during the allowable lane closure hours of approximately 9:00 AM to 3:30PM. No daytime access will be available to Calamo Street through the…

  • Work Update for Week of May 19th

    During the week of May 19th, we will continue the sanitary sewer main pipe replacement work east of the Ridgeway Drive intersection. Daily detours will be installed during the allowable lane closure hours of approximately 9:00AM to 3:30PM. No daytime access will be available to Calamo Street through the Ridgeway Drive intersection. All local traffic…

  • Work Update for Week of May 12th

    During the week of May 12th, we will continue the sanitary sewer main pipe replacement work east of the Ridgeway Drive intersection. Daily detours will be installed during the allowable lane closure hours of approximately 9:00AM to 3:30PM. No daytime access will be available to Calamo Street through the Ridgeway Drive intersection. All local traffic…

  • Work Update for Week of May 5th

    During the week of May 5th, we will continue the sanitary sewer main pipe replacement work east of the Ridgeway Drive intersection. Daily detours will be installed during the allowable lane closure hours of approximately 9:00AM to 3:30PM. No daytime access will be available to Calamo Street through the Ridgeway Drive intersection. All local traffic…

  • Work Update for Week of April 28th

    During the week of April 28th, we do not have any changes to our work schedule. The sanitary sewer main pipe replacement work will continue to the east of the Ridgeway Drive intersection. Daily detours will be installed during the allowable lane closure hours of approximately 9:00AM to 3:30PM. No daytime access will be available…

  • Work Update for Week of April 21st

    During the week of April 21st,  we will continue the sanitary sewer main pipe replacement work east of the Ridgeway Drive intersection. Daily detours will be installed during the allowable lane closure hours of approximately 9:00AM to 3:30PM. No daytime access will be available to Calamo Street through the Ridgeway Drive intersection. All local traffic…

  • Work Update for Week of April 14th

    During the week of April 14th,  we will continue the sanitary sewer main pipe replacement work east of the Ridgeway Drive intersection. Daily detours will be installed during the allowable lane closure hours of approximately 9:00AM to 3:30PM. No daytime access will be available to Calamo Street through the Ridgeway Drive intersection. All local traffic…

  • Work Update for Week of April 7th

    During the week of April 7th,  we will continue the sanitary sewer main pipe replacement work. The work will still be on Calamo Street east of the Ridgeway Drive intersection.  Daily detours will be installed during the allowable lane closure hours of approximately 9:00AM to 3:30PM. No daytime access will be available to Calamo Street…

  • Work Update for Week of March 31st

    During the week of March 31st,  we will complete the temporary bypass installation and begin the sanitary sewer main pipe replacement work. The sanitary sewer work will begin on Calamo Street directly east of the Ridgeway Drive intersection.  Over the next several months we will continue working east on Calamo Street with the replacement work.…

  • Work Update for Week of March 24th

    During the week of March 24th,  we will continue performing the same construction operations as last week on Calamo Street between Wren Drive and Spring Road. Any flagging or detour operations that occur will be during the allowable lane closure hours of approximately 9:00 AM to 3:30 PM. Work to be performed this week: This…